Below is the planned
schedule for the paving of Nantasket Road. This schedule is weather sensitive
and may change due to adverse weather conditions.
September 7th through September 11th
The crews will be
mobilizing their equipment and conducting some field engineering and surveys.
During these two-days, they will be setting up erosion controls and doing miscellaneous
prep work.
September 8th through September 12th
A crew will be lowering
and plating castings
September 11th through September 15th
The reclaiming operation
will take place
September 15th through September 18th
A binder course will be
put on the roadway
September 18th through September 19th
A binder course will put
on the affected driveways
September 19th through September 21st
Utility structures in the
roadway will be rebuilt and adjusted as needed
September 22nd
The surface course will be
applied to the roadway
September 25th through September 26th
The surface course will be
applied to the affected driveways
September 27th
The roadway will have the
lines painted
September 25th through September 29th
Loaming and seeding of the
affected areas will be done
September 28th through September 29th
The crews will be leaving